Heber's Bypass Pays for the Land It Takes. Neighbors Along 1300 South Get No Check.

"Essentially, you're asking if a change to their viewshed is compensated, and the answer is no."

That is how UDOT's Naomi Kisen answered Heber City Mayor Heidi Franco in January, as the Park Record reported. Franco had asked whether people who own property beside the proposed Heber Valley Corridor would be paid if noise, traffic, or reduced visibility lowered their values. UDOT's own Draft EIS FAQ describes its compensation policy. UDOT says it pays fair market value when all or part of a property is needed for the project and does not pay for noise, traffic, or visual impacts when no property is taken.

The Draft EIS counts far more neighbors than takings

UDOT's January 2026 Alternative B fact sheet covers the preferred off-US-40 route. It lists the property impacts next to the noise impacts, and the gap between the two is the whole story.

Alternative B, Draft EIS, January 2026 Count
Relocations 6 residences, 2 businesses
Full acquisitions 32 parcels, 121 acres
Partial acquisitions 124 parcels, 207 acres
Noise receptors modeled above criteria 277, including 273 residences
Estimated cost, 2026 dollars $760.5 million

Eight relocations sit on one side of the ledger and 273 residences with modeled noise above criteria sit on the other. That is why Franco pushed back. "If you were to build a double-decker highway, when we ran on the campaign trail, we heard that people would sell their homes there and have to literally move out of the state because there's nowhere else they could afford to live," she said, according to the Park Record.

What the elevated lanes on 1300 South look like up close

Most of those neighbor impacts cluster along 1300 South, where the Draft EIS puts the corridor's east-west connection. Through traffic would run on two elevated lanes, one in each direction, with one-way frontage roads at ground level on both sides. The structure tapers down to grade near Industrial Parkway and is tallest, at 24 feet, near 300 West.

For a house near this stretch, the practical questions are about which streets still connect. According to the Draft EIS FAQ, the plan would:

  • Keep bridges under the elevated lanes at 300 West, US-189, and Daniels Road
  • Leave no bridge at Industrial Parkway, so drivers there could only turn right on and off the frontage roads
  • End Southfield Road in a cul-de-sac near 1200 South, which adds up to about 1.5 miles for a few homes heading to US-189. That drops to about 1 mile once the city finishes its planned 1200 South connection.
  • Send Country Meadows residents to the interchange by way of 600 West and SR-113, about a half-mile longer, though UDOT is considering realigning Southfield Road to the high school intersection

UDOT describes the result for neighborhoods near 1300 South as "a mix of outcomes." Residential streets would see less traffic, while some trips to the new corridor or US-189 would get longer.

The route got this tight partly because of history. Heber City and Wasatch County preserved a bypass corridor in 2006 and 2007, and in places it is as narrow as 84 feet. The freeway design needs 250 feet. The Draft EIS shifts west of that preserved strip between SR-113 and 1300 South, which avoids the new substation, the Kimball Villas senior living community, and the Parkview Place housing development. A buyer who checked an old city plan and assumed the corridor was a thin, settled line would be reading a map the project has already outgrown.

Noise walls get decided by a vote later

Noise walls aren't guaranteed. The Draft EIS found barriers feasible and reasonable on the north side of 1300 South between about 300 West and 800 West, which would benefit residents on 1250 South and Meadow Walk Drive. Those residents would vote on the walls during final design.

The fine print sets expectations lower than that summary suggests. Of 24 noise barriers modeled for Alternative B, three met both the acoustic and cost criteria. UDOT says it won't make a final decision until final design, after it has refined utility and right-of-way costs, and that recommending a barrier for a vote is not a commitment to build it. For a home on one of those streets, the wall is a possibility that will be settled years after closing.

The line can still move before spring 2027

The route isn't fixed yet. UDOT's project update, revised October 23, 2026, says it expects to publish the Final EIS and Record of Decision in spring 2027. Alternative B is still the preferred alternative, and UDOT is weighing three design refinements:

"Shifting the elevated road further south, reducing impacts to neighborhoods and rural character in response to community concerns."

That is the language for 1300 South. The other two refinements would move the North Fields segment east near 600 West and add bicycle and pedestrian crossings at the SR-113 interchange. UDOT says it will screen these options with the same criteria it used earlier in the study.

The southward shift traces back to local officials. Mayor Franco and all five council members wrote that they would have preferred the 1300 South leg to run farther south through undeveloped land, TownLift reported in May. UDOT project manager Craig Hancock called the possible adjustments "design refinements" rather than a new alternative. In August, the Park Record reported that UDOT had moved its decision from the end of 2026 to spring 2027 and had secured $1 million from the Utah Transportation Commission to study the changes, along with more traffic and wetlands analysis. It also has more than 700 public comments to answer.

A southward shift could change which homes are counted as neighbors and which parcels fall in the acquisition column.

Spring 2027 starts a longer wait

A Record of Decision settles the alignment, but it doesn't fund it. UDOT's FAQ says there is currently no money for final design, right-of-way acquisition, or construction. After the decision, the project goes into the state's prioritization process. State funds are already programmed through 2031, with a draft through 2032, which puts construction "6 years out at a minimum, likely more." UDOT also says there is no special Olympics funding for the corridor. The project could be built in phases depending on how the money comes in, though no phasing plan has been studied.

The acquisition timing matters most for a buyer. The Draft EIS says decisions on full acquisitions and relocations come during the acquisition phase, which happens shortly before construction, and that property impacts may change in final design. A home near 1300 South could change hands more than once while a mapped but unfunded corridor sits next to it. Each buyer in that chain inherits the same uncertainty.

The North Fields carry a different set of commitments

At the north end, the corridor would cut west off US-40 at Potter Lane/College Way into a four-lane extension through the North Fields, then join the Western Corridor at 900 North. UDOT has committed to no new access points on the corridor between Potter Lane and SR-113. It also plans to make the North Fields a priority for wetland mitigation, at 2 to 15 acres for every acre impacted, with mitigated land taken out of private ownership.

Local governments are adding their own protections. The memorandum of understanding between Heber City and Wasatch County is now official, the Park Record reported on October 27. It moves the city's boundary line from Mill Road to the Provo River and ties Heber's annexation agreements to whether the city may develop past 850 North on the west side of US-40. The memorandum is not binding the way an interlocal agreement is, and the two governments are still working on an interlocal agreement that would include Midway City. Near the North Fields, the bypass comes with long-term open-space commitments attached. Along 1300 South, it comes with frontage roads.

Where the traffic relief lands

The traffic payoff is real, and it lands somewhere else. UDOT forecasts less traffic on River Road and Mill Road under Alternative B and no change on 3000 South. On Main Street, the fact sheet models local travel time in 2050 at 20 minutes 30 seconds with no project and 10 minutes 15 seconds with Alternative B. Southbound queues at 500 North drop from 17,100 feet to 700. Downtown and the River Road and Mill Road corridors get the benefits, and the costs fall mostly on 1300 South.

Questions buyers ask about the bypass

Has UDOT picked the final route? No. Alternative B is the preferred alternative, and the Final EIS and Record of Decision are expected in spring 2027. Refinements at 1300 South and 600 West are still being evaluated.

Where can I see how a specific street is affected? UDOT posts its Draft EIS display boards, which show access changes at specific locations. Its project page carries the latest schedule updates.

This post is general information, not legal, tax, or financial advice. If you're weighing a property near the corridor, confirm how these rules apply to it with an attorney or other qualified professional.

If you're looking at homes near 1300 South, Southfield Road, or the North Fields, I'm happy to go through the Draft EIS maps with you. Cathy Schaede | Let's Connect.

A Higher Standard of Real Estate Service

Experience a seamless, results-driven approach backed by local expertise, strategic negotiation, and personalized attention.

Follow Me on Instagram